동시공학 및 LOB를 사용한 반복 프로젝트 공기단축 방법론
민규태 ( Min Gyu-tae ),이홍철 ( Lee Hong-chul ),리현군 ( Li Xian-jun ),이동은 ( Lee Dong-eun ) 한국건축시공학회 2018 한국건축시공학회 학술발표대회 논문집 Vol.18 No.1
Various methods that crash the project completion time have been studied. Line-of-Balance (LOB) is well accepted as a useful method that enables steady resource utilization without frequent hire-and-fire of resources for a project having repetitive units. Existing studies involved in LOB-CPM focuses on thesis such as resource leveling and optimization in construction scheduling community. However, crashing methods are not arrived at a full maturity in LOB scheduling, because no one handles steady resource utilization while keeping activity-relationships. This paper proposes a method that crashes project completion time by hybridizing concurrent engineering and LOB scheduling without using additional resources.